Project Duration
Stipulated Date of Commencement
October 19 2020
Stipulated Date of Completion /
Likely Date of Completion October 18 2024
Likely Date of Completion October 18 2024
Status
87%
Completed
Cost (₹)
Estimated at
₹ 347,778.00
Awarded for
₹ 347,778.00
Project highlights
Maintenance of lift at GMC
Contractors
M/s. Otis Elevator Company (India) Ltd.
Consultants
In-house
(GSIDC)