Project Duration
Stipulated Date of Commencement October 19 2020
Stipulated Date of Completion /
Likely Date of Completion
October 18 2024
Status
87%
Completed
Cost (₹)
Estimated at ₹ 347,778.00
Awarded for ₹ 347,778.00

Project highlights

Maintenance of lift at GMC

 
Gallery Image
Contractors
M/s. Otis Elevator Company (India) Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Redesigning and reconstruction of existing buildings and additional construction and new administration and training block for Fire station at Panaji,Goa.

View Project
Similar Project

Construction of New District & Sessions Court Complex at Merces, Tiswadi – Goa: Audio Video system.

View Project
Similar Project

Construction of Office of Inspectorate of Factories & Boilers at Altinho, Panaji-Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.