Project Duration
Stipulated Date of Commencement
March 17 2024
Stipulated Date of Completion /
Likely Date of Completion September 16 2024
Likely Date of Completion September 16 2024
Status
30%
Completed
Cost (₹)
Estimated at
₹ 7,613,773.00
Awarded for
₹ 6,988,850.00