Project Duration
Stipulated Date of Commencement
February 25 2014
Stipulated Date of Completion /
Likely Date of Completion May 24 2015
Likely Date of Completion May 24 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 61,975,499.00
Awarded for
₹ 73,269,958.00
Project highlights
Football Playground with dressing rooms and stand, Cricket pratice pitches, Gymnasium, Multipurpose hall, etc.
Contractors
M/s. D. S. Kulkarni Developers Ltd.
Consultants
M/s. Gurudutt Sanzgiri