Project Duration
Stipulated Date of Commencement
September 29 2018
Stipulated Date of Completion /
Likely Date of Completion July 14 2019
Likely Date of Completion July 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,039,750.00
Awarded for
₹ 9,234,882.08
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Nilambari Construction
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs & Upgradation and maintenance of Govt. Schools in the State of Goa. Package IB (Bardez Taluka)
View Project
Repairs/Upgradation and Maintenance of Government Schools in the State of Goa – Civil, Plumbing and Electrical works in :-Bardez Taluka – GPS Carambolim.
View Project