Project Duration
Stipulated Date of Commencement September 29 2018
Stipulated Date of Completion /
Likely Date of Completion
July 14 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,039,750.00
Awarded for ₹ 9,234,882.08

Project highlights

Repairs/ Upgradation & Maintenance of schools