Project Duration
Stipulated Date of Commencement March 18 2004
Actual Date of Completion November 27 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 100,000,000.00
Awarded for ₹ 79,443,000.00

Project highlights

The Patto Bridge is 200 mts. in length, 12 mts. wide having geometrical features similar to the existing Patto Bridge. The foundations are pile foundations.

 
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. S.N.Bhobe & Associates Pvt. Ltd
 

See Similar Projects

Upgradation & beautification of road network from Seraulim to Colva beach – Phase I.

View Project

Construction of Jetty at Brittona – Additional works.

View Project

Khareband Bridge.

View Project