Project Duration
Stipulated Date of Commencement March 18 2004
Stipulated Date of Completion /
Likely Date of Completion
November 17 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 100,000,000.00
Awarded for ₹ 79,443,000.00

Project highlights

The Patto Bridge is 200 mts. in length, 12 mts. wide having geometrical features similar to the existing Patto Bridge. The foundations are pile foundations.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. S.N.Bhobe & Associates Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Widening of road in Calangute – Baga.

View Project
Similar Project

Improvement and Upgradation of road network at Piligao, Curti, Ponda Town and Chodan.

View Project
Similar Project

Construction of bridge between Tharmas to Ozari Sangaowada in Dhargal Constituency.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.