Project Duration
Stipulated Date of Commencement
March 03 2007
Actual Date of Completion
December 19 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,969,028.00
Awarded for
₹ 186,209,408.98
Final Cost of Project
₹ 477,277,039.00
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
M/s. IVRCL Infrastructures & Projects Limited
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd., M/s. Intertek Architects & Consultants Pvt. Ltd.