Project Duration
Stipulated Date of Commencement
November 24 2016
Actual Date of Completion
March 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,967,188.00
Awarded for
₹ 21,657,524.60
Final Cost of Project
₹ Rs. 2,33,39,196.00
Project highlights
Maintenance works of Goa Dental college
Contractors
M/s. Deshpande Constructions
Consultants
Inhouse