Project Duration
Stipulated Date of Commencement
November 24 2016
Stipulated Date of Completion /
Likely Date of Completion November 23 2017
Likely Date of Completion November 23 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,967,188.00
Awarded for
₹ 21,657,524.60
Project highlights
Maintenance works of Goa Dental college
Contractors
M/s. Deshpande Constructions
Consultants
In-house (GSIDC)