Project Duration
Stipulated Date of Commencement
November 19 2010
Actual Date of Completion
January 04 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ -
Awarded for
₹ 99,55,323.00
Contractors
M/s. Bry Air (Asia) Pvt. Ltd.
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.