Project Duration
Stipulated Date of Commencement March 04 2007
Stipulated Date of Completion /
Likely Date of Completion
July 03 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,110,745.00
Awarded for ₹ 5,686,390.00

Project highlights

Land filling and construction of retaining wall

 
Gallery Image
Contractors
M/s. Madanant Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s.Rajiv Gandhi Kala Mandir

View Project
Similar Project

Lift/ Elevator Work

View Project
Similar Project

Package III (VP Azossim-Mandur-Dongrim & VP Neura).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.