Project Duration
Stipulated Date of Commencement
March 27 2007
Stipulated Date of Completion /
Likely Date of Completion March 26 2008
Likely Date of Completion March 26 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 54,371,959.00
Awarded for
₹ 69,139,000.00
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of Swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.
100% completed
Project Duration
Stipulated Date of Commencement
February 12 2009
Stipulated Date of Completion /
Likely Date of Completion May 11 2009
Likely Date of Completion May 11 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,71,379.00
Awarded for
₹ 47,00,750.52
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates
See Similar Projects
Extension / Upgradation of Government College of Arts, Science & Commerce at Khandola, Marcel, Goa
View Project
Construction of Anganwadi Centres from NABARD Assistance.
View Project
Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.
View Project