Project Duration
Stipulated Date of Commencement
March 27 2007
Actual Date of Completion
February 23 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 54,371,959.00
Awarded for
₹ 69,139,000.00
Final Cost of Project
₹ 73,987,035.00
Contractors
M/s. IVRCL Infrastructure & Projects Ltd., M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Construction of swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.
100% completed
Project Duration
Stipulated Date of Commencement
February 12 2009
Stipulated Date of Completion /
Likely Date of Completion June 07 2009
Likely Date of Completion June 07 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,71,379.00
Awarded for
₹ 47,00,750.52
Contractors
M/s. Rohit Equipments
Consultants
M/s. Datta Kare Associates
See Similar Projects
Construction of building for boys’ hostel at Goa University Campus – Civil & Plumbing works
View ProjectReconstruction of Government High School at Betoda, Goa.
View ProjectInfrastructure Works For Sanjay Centre For Special Education at Porvorim-SH:Fire safety and exit signages work
View Project