Project Duration
Stipulated Date of Commencement January 14 2016
Stipulated Date of Completion /
Likely Date of Completion
August 13 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,883,534.00
Awarded for ₹ 54,586,026.00

Project highlights

1. The Bridge was used to facilitate the Defence Expo 2016.
2. Length of the bridge and no. of spans: Single span of 24.75 mt long
3. Loading: One lane of Class 70R wheeled/ tracked or 2 lanes of Class ‘A’ which is critical.
4. Type & Depth of Foundations: Pile Foundation – On Fatorpa Side 30.2 m & on Balli Side 26.19 m
5. Sub-Structure: RCC
6. Bearing: POT PTFE
7. Superstructure: Composite steel plate girder, RCC deck slab.
8. Carriageway and footpath widths: 7.5 mts. Carriageway & 1.5 m footpath on each side.
9. Details of wearing coat: 50 mm D.B.M. with 25mm Polymerized Modified Bitumen, 3mm waterproofing membrane
10. Details of Expansion Joints: Strip seal expansion joints.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.

View Project
Similar Project

Design & Construction of Bridge of Cumbarjua, Goa on RCC Bored Pile Foundaton.

View Project
Similar Project

Construction of Bus stand at Mapusa, Goa – Miscellaneous work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.