Project Duration
Stipulated Date of Commencement
March 02 2007
Actual Date of Completion
November 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 107,796,055.00
Awarded for
₹ 134,010,749.00
Final Cost of Project
₹ 446,418,072.00
Project highlights
Ravindra Bhavan
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd., M/s. Intertek Architects & Consultants Pvt. Ltd.