Project Duration
Stipulated Date of Commencement
July 03 2015
Actual Date of Completion
July 31 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,759,455.25
Awarded for
₹ 36,700,220.20
Final Cost of Project
₹ 45,780,886.00
Project highlights
Construction of new Multipurpose hall building for Panchayat
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Oracle Structural Consultants