Project Duration
Stipulated Date of Commencement
October 29 2008
Actual Date of Completion
June 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 133,955,490.42
Awarded for
₹ 211,937,309.40
Final Cost of Project
₹ 371,334,070.00
Contractors
M/s.Silpa Projects and Infrastructure (I) Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.,