Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Civil, Plumbing & Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
January 06 2009
Stipulated Date of Completion /
Likely Date of Completion March 05 2010
Likely Date of Completion March 05 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,31,78,550.00
Awarded for
₹ 76,513,097.00
Project highlights
The Panchayat Ghar is a G+1 RCC framed structure having shops, Bank, Post Office, Toilet for ladies and gents on the Ground floor. The first floor complrises of a Community Hall with a capaity of 400 seats with dining area, green rooms for ladies and gents, Office for Panchayat, Gymnasium, Library. Toilet for ladies and gents etc.
Contractors
M/s. Acron Developers Pvt. Ltd.
Consultants
M/s. Vijaykumar Sawant Associates
2
Phase I : Land Development.
100% completed
Project Duration
Stipulated Date of Commencement
February 22 2008
Stipulated Date of Completion /
Likely Date of Completion August 21 2008
Likely Date of Completion August 21 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,780,533.00
Awarded for
₹ 9,700,990.00
Project highlights
Land filling and construction of retaining wall
Contractors
M/s. Rohit Equipments
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Providing and Maintaining Event Management facilities for Exposition 2014 at Old Goa
View Project
Stage Lighting work
View Project
Supply, Installation, Testing and Commissioning of street light poles and fixtures along with allied electrical works for the stretch from Odxel junction to GMC
View Project