Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Civil, Plumbing & Electrical works.
100% completed
Project Duration
Stipulated Date of Commencement
January 06 2009
Stipulated Date of Completion /
Likely Date of Completion March 05 2010
Likely Date of Completion March 05 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,31,78,550.00
Awarded for
₹ 76,513,097.00
Project highlights
The Panchayat Ghar is a G+1 RCC framed structure having shops, Bank, Post Office, Toilet for ladies and gents on the Ground floor. The first floor complrises of a Community Hall with a capaity of 400 seats with dining area, green rooms for ladies and gents, Office for Panchayat, Gymnasium, Library. Toilet for ladies and gents etc.
Contractors
M/s. Acron Developers Pvt. Ltd.
Consultants
M/s. Vijaykumar Sawant Associates
2
Phase I : Land Development.
100% completed
Project Duration
Stipulated Date of Commencement
February 22 2008
Stipulated Date of Completion /
Likely Date of Completion August 21 2008
Likely Date of Completion August 21 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,780,533.00
Awarded for
₹ 9,700,990.00
Project highlights
Land filling and construction of retaining wall
Contractors
M/s. Rohit Equipments
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Book Cutting Machine.
View Project
Public Works in Sankhali Constituency
View Project
Rejuvenation of cluster of lanes of Altinho Steps Phase I
View Project





