Project Duration
Stipulated Date of Commencement
July 11 2014
Stipulated Date of Completion /
Likely Date of Completion August 10 2014
Likely Date of Completion August 10 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,76,42,076.00
Awarded for
₹ 19,688,390.00
Contractors
M/s. Floor-Space
Consultants
M/s. Effective Architectural Services
See Similar Projects
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Pernem Taluka : Construction of Panchayat Complex cum Multipurpose Hall at V. P. Querim – Tiracol
View Project
Upgradation and Renovation of Market at Santemol, Raia (Tinto).
View Project
Signages work
View Project





