Project Duration
Stipulated Date of Commencement
October 24 2021
Stipulated Date of Completion /
Likely Date of Completion January 23 2023
Likely Date of Completion January 23 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,468,979.00
Awarded for
₹ 18,220,219.00
Project highlights
Upgradation of existing Panchayat and provision of shops for social welfare group
Contractors
M/s. Sun Infrastructures
Consultants
M/s. Vijaykumar Sawant & Associates,