Project Duration
Stipulated Date of Commencement
August 26 2016
Stipulated Date of Completion /
Likely Date of Completion November 25 2017
Likely Date of Completion November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,051,673.00
Awarded for
₹ 14,133,458.98
Project highlights
(1) Ground floor consists of 1 nos. of shop of size 2.35 x 4.54.mt
(2) First floor consists of Panchayat Office, seperate Talathis Office, Sarpanch , Secretary and Conference room, Animal Husbandary & Electricity Dept and seperate toilets.
Contractors
M/s.Vaishnavi Infrastructure
Consultants
M/s. Creative Abode
See Similar Projects
Upgradation of existing Neura village Panchayat ghar building for V.P.Neura under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) scheme.
View Project
Redevelopment of Panaji Municipal Market – Balance work in Phase II.
View Project
Upgradation of Outlet of Goa State Horticulture Corporation Ltd. at Altinho to the standard of Modern super market.
View Project