Project Duration
Stipulated Date of Commencement
June 21 2008
Stipulated Date of Completion /
Likely Date of Completion August 04 2008
Likely Date of Completion August 04 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,783,101.00
Awarded for
₹ 1,872,218.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.