Project Duration
Stipulated Date of Commencement February 19 2010
Stipulated Date of Completion /
Likely Date of Completion
June 18 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,344,768.00
Awarded for ₹ 76,61,699.00
 
Gallery Image
Contractors
M/s. Speedfrost Services
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.

View Project
Similar Project

Construction of 500 Bedded District Hospital At Margao, Goa – LV System

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa S.H.: Maintenance Contract for the UPS systems installed at Upgraded Cottage Hospital, Chicalim for a period of three years (2019-2022)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.