Project Duration
Stipulated Date of Commencement November 26 2008
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,896,304.00
Awarded for ₹ 8,221,418.85

Project highlights

The work includes remodeling the wards, replacing flooring, dado, door, windows, false ceiling, internal painting, etc., replacing and realigning internal plumbing network, sanitary fixtures etc.

 
Contractors
M/s. A. Ponnuraj
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 