Project Duration
Stipulated Date of Commencement
April 26 2008
Actual Date of Completion
October 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,378,896.00
Awarded for
₹ 26,653,000.00
Contractors
M/s. Genuine Medica Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.