Project Duration
Stipulated Date of Commencement October 04 2007
Stipulated Date of Completion /
Likely Date of Completion
January 03 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,314,729.00
Awarded for ₹ 8,015,705.00
 
Gallery Image
Contractors
M/s. Paradyne Infotech Limited
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Minor maintenance and renovation works at Goa Dental College and Hospital, Bambollim,Goa.

View Project
Similar Project

Face-lift to Tisk Usgao Hospital building including staff quarters

View Project
Similar Project

External electrical works at area around new Library Building and Power supply to new Library building at GMC Complex.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.