Project Duration
Stipulated Date of Commencement
February 28 2009
Stipulated Date of Completion /
Likely Date of Completion June 27 2009
Likely Date of Completion June 27 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,988,688.00
Awarded for
₹ 12,968,300.00
Project highlights
False ceiling done in most of the areas in the Central Library
Contractors
M/s. Damian de Goa
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
See Similar Projects
Desktop computers, printers & scanners.
View Project
CCTV Works
View Project
Fire Fighting, Fire Alarm and PA System.
View Project





