Status
100%
Completed

Project highlights

Renovation/Refurbishment of existng building

 
 

Sub Works

This project involved 21 sub works. The details of the same available below

1

Catwalk & Grid work

100% completed
 
Project Duration
Stipulated Date of Commencement January 25 2014
Stipulated Date of Completion /
Likely Date of Completion
April 15 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,79,96,453.11
Awarded for ₹ 31,090,851.72
Final Cost of Project ₹ 28,463,921.00
 
Contractors
M/s. ASP Water and Power Projects Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
2

False Ceiling & Acoustic work

100% completed
 
Project Duration
Stipulated Date of Commencement March 03 2014
Stipulated Date of Completion /
Likely Date of Completion
March 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,44,66,205.12
Awarded for ₹ 78,429,459.65
Final Cost of Project ₹ 106,979,376.00
 
Contractors
M/s.Srishti Enterprises
Consultants
M/s. Effective Architectural Services
3

Interior Work

100% completed
 
Project Duration
Stipulated Date of Commencement July 11 2014
Stipulated Date of Completion /
Likely Date of Completion
April 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,76,42,076.00
Awarded for ₹ 19,688,390.00
Final Cost of Project ₹ 23,707,508.00
 
Contractors
M/s. Floor Spaces
Consultants
M/s. Effective Architectural Services
4

Arena Work

100% completed
 
Project Duration
Stipulated Date of Commencement March 01 2015
Stipulated Date of Completion /
Likely Date of Completion
March 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 13,003,136.00
Awarded for ₹ 14,409,292.00
Final Cost of Project ₹ 15,380,449.00
 
Contractors
M/s.Srishti Enterprises
Consultants
M/s. Effective Architectural Services
5

External Development Work

100% completed
 
Project Duration
Stipulated Date of Commencement March 01 2015
Stipulated Date of Completion /
Likely Date of Completion
April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,25,22,220.00
Awarded for ₹ 1,52,00,000.00
Final Cost of Project ₹ 26,814,315.00
 
Contractors
M/s. Shivam Infratech
Consultants
M/s. Effective Architectural Services
6

Landscaping Work

100% completed
 
Project Duration
Stipulated Date of Commencement May 02 2015
Stipulated Date of Completion /
Likely Date of Completion
April 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,325,881.00
Awarded for ₹ 1,127,228.50
Final Cost of Project ₹ 1,761,777.00
 
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Effective Architectural Services
7

One time deep Cleaning

100% completed
 
Project Duration
Stipulated Date of Commencement February 02 2016
Stipulated Date of Completion /
Likely Date of Completion
March 01 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 272,000.00
Awarded for ₹ 203,864.00
Final Cost of Project ₹ 192,176.00
 
Contractors
M/s. Ecoclean System and solutions
Consultants
M/s. Effective Architectural Services
8

Providing Private security Services

100% completed
 
Project Duration
Stipulated Date of Commencement February 02 2016
Stipulated Date of Completion /
Likely Date of Completion
July 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 225,000.00
Awarded for ₹ 225,000.00
Final Cost of Project ₹ 393,012.00
 
Contractors
M/s. Rudreshwar Industrial Security Services
Consultants
M/s. Effective Architectural Services
9

Removal of Rubbish/Debris and leveling of parking area

100% completed
 
Project Duration
Stipulated Date of Commencement June 21 2017
Stipulated Date of Completion /
Likely Date of Completion
July 05 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 653,125.00
Awarded for ₹ 863,265.00
Final Cost of Project ₹ 587,664.00
 
Contractors
M/s. A.G. Pushpakaran
Consultants
M/s. Effective Architectural Services
10

Arranging Scaffolding

100% completed
 
Project Duration
Stipulated Date of Commencement May 30 2018
Stipulated Date of Completion /
Likely Date of Completion
June 10 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,500.00
Awarded for ₹ 27,500.00
Final Cost of Project ₹ 192,500.00
 
Contractors
M/s. Sharavi Constructions Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
11

supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s Rajiv Gandhi Kala Mandir

100% completed
 
Project Duration
Stipulated Date of Commencement May 02 2016
Stipulated Date of Completion /
Likely Date of Completion
May 22 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,516,970.00
Awarded for ₹ 3,212,332.00
 
Contractors
M/s Installation Services
Consultants
M/s. Effective Architectural Services
12

Audio-Video Works

100% completed
 
Project Duration
Stipulated Date of Commencement February 26 2014
Stipulated Date of Completion /
Likely Date of Completion
May 15 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 40,096,751.00
Awarded for ₹ 31,460,654.00
Final Cost of Project ₹ 31,673,914.32
 
Contractors
M/s Hi Tech Audio Systems Pvt Ltd
Consultants
M/s. Effective Architectural Services
13

CCTV Works

100% completed
 
Project Duration
Stipulated Date of Commencement December 28 2014
Stipulated Date of Completion /
Likely Date of Completion
April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,309,655.00
Awarded for ₹ 2,956,518.00
Final Cost of Project ₹ 2,691,227.96
 
Contractors
M/s. Psytech Infosolutions (India) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
14

Supply, erection and commissioning of Diesel Generator Sets

100% completed
 
Project Duration
Stipulated Date of Commencement February 24 2014
Stipulated Date of Completion /
Likely Date of Completion
May 13 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,179,260.00
Awarded for ₹ 3,887,000.00
Final Cost of Project ₹ 3,887,000.00
 
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In House
15

Electrical Work

100% completed
 
Project Duration
Stipulated Date of Commencement November 13 2010
Stipulated Date of Completion /
Likely Date of Completion
October 06 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,016,915.00
Awarded for ₹ 11,962,654.36
Final Cost of Project ₹ 10,494,521.06
 
Contractors
M/s Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
16

External Lighting Works

100% completed
 
Project Duration
Stipulated Date of Commencement February 08 2015
Stipulated Date of Completion /
Likely Date of Completion
April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,507,609.00
Awarded for ₹ 1,571,883.00
Final Cost of Project ₹ 1,425,287.00
 
Contractors
M/s. Goa Friend’s Engineering & Electricals Pvt. Ltd
Consultants
M/s. Effective Architectural Services
17

HVAC Works.

100% completed
 
Project Duration
Stipulated Date of Commencement July 28 2011
Stipulated Date of Completion /
Likely Date of Completion
April 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,868,930.00
Awarded for ₹ 18,856,723.50
Final Cost of Project ₹ 38,878,981.00
 
Contractors
M/s Shree Manguirish Air Conditioning Company
Consultants
M/s. Effective Architectural Services
18

Lift/ Elevator Work

100% completed
 
Project Duration
Stipulated Date of Commencement August 10 2010
Stipulated Date of Completion /
Likely Date of Completion
May 30 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,852,975.00
Awarded for ₹ 4,026,350.00
Final Cost of Project ₹ 4,026,350.00
 
Contractors
M/s ThyssenKrupp (I) Pvt Ltd
Consultants
M/s. Effective Architectural Services
19

Stage Drapery and Lighting Work

100% completed
 
Project Duration
Stipulated Date of Commencement August 03 2014
Stipulated Date of Completion /
Likely Date of Completion
October 27 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 20,161,848.00
Awarded for ₹ 16,940,378.00
Final Cost of Project ₹ 15,591,756.90
 
Contractors
M/s Canara Lighting Industries Pvt Ltd
Consultants
M/s. Effective Architectural Services
20

Supply, Installation, Testing and Commissioning of APFC panel and UPS Works

100% completed
 
Project Duration
Stipulated Date of Commencement January 12 2014
Stipulated Date of Completion /
Likely Date of Completion
July 21 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,223,672.00
Awarded for ₹ 3,374,000.00
Final Cost of Project ₹ 3,389,942.00
 
Contractors
M/s. GMP Technical Solutions Pvt. Ltd
Consultants
M/s. Effective Architectural Services
21

Supply, Installation, Testing and Commissioning of 120 KVA UPS.

100% completed
 
Project Duration
Stipulated Date of Commencement January 02 2020
Stipulated Date of Completion /
Likely Date of Completion
February 07 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,311,387.44
Awarded for ₹ 1,590,670.00
 
Contractors
M/s Techser Power Solutions (P) Ltd
Consultants
M/s. Effective Architectural Services

See Similar Projects

Painting Landscaping and other ancillary works along DB Road for IFFI 2017

View Project

Fire Hydrant / Alarm System.

View Project

Integration of Renovation of Ravindra Bhavan & Construction of IInd Phase of Ravindra Bhavan at Curchorem-Goa, Construction of Sports Complex at Curchorem-Goa, Construction of Bus Stand at Curchorem with related Infrastructure and CCMC Admin Building at Curchorem.

View Project
x