Project Duration
Stipulated Date of Commencement
November 25 2010
Stipulated Date of Completion /
Likely Date of Completion February 25 2012
Likely Date of Completion February 25 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 60,710,082.00
Awarded for
₹ 62,269,573.00
Project highlights
Construction of Bus stand having provison of 10 parking bay for buses, 4 commercial shops and other facilities. A mutipurpose hall with seating capacity of 800 with stage and changing rooms is attached to the Bus stand.
Contractors
M/s. Shilpi Constructions
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Upgradation of the Road connecting Integrated School Complex to NH17 – Civil, Plumbing & Electrical works
View Project
Construction of Jetty at Brittona – Additional works.
View Project
Improvement / Hot mixing of roads in Arpora – Candolim.
View Project





