Project Duration
Stipulated Date of Commencement
May 26 2006
Stipulated Date of Completion /
Likely Date of Completion August 25 2006
Likely Date of Completion August 25 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,482,879.00
Awarded for
₹ 44,187,674.21
Project highlights
Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, construction of culverts, providing gutters and cross drainages wherever required. The approximate length of the road is around 5.72 kms.
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Additional works from Sai Service Junction to Training College Junction at Porvorim, Goa
View Project
Widening of roads and relocation of structures in Fatorda Constituency – Phase II – Illumination of Footpath from Colva Circle to Ravindra Bhavan Circle at Fatorda, Margao, Goa
View Project
Construction of Pirna Ozrim bridge including approaches.
View Project





