Status
100%
Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 4 sub works. The details of the same available below

1

Phase I : Land Development.

100% completed
 
Project Duration
Stipulated Date of Completion /
Likely Date of Completion
June 02 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,007,426.03
Awarded for ₹ 3,694,673.60

Project highlights

• Built-up area : 2670 sq. m.
• Construction of bus stand with amenities such as shops, cafeteria, wash rooms etc.
• Roof is designed as a wave supported by columns and trusses representing palm trees.
• Bus entries and exits are separate and independent from commuter entry.
• Floor height in the bays is aligned with the first step of the bus for easier access.
• Smooth traffic flow is ensured including that of taxis and rickshaws.
• Provision for taxi stand, motor cycle stand, rickshaw stand, etc.
• 10 nos. parking bays for scheduled buses. Besides there are bays for idle parking of buses.
• Parking for private vehicles.
• Rest room for passengers, drivers and staff.

 
Contractors
Contractors
M/s.Sunil Construction
Consultants
Consultants
M/s. Rahul Deshpande & Associates
2

Phase II

100% completed
 
Project Duration
Stipulated Date of Commencement January 27 2004
Stipulated Date of Completion /
Likely Date of Completion
July 27 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,989,680.00
Awarded for ₹ 28,751,965.00
 
Contractors
Contractors
M/s.D. S. Contractors Pvt. Ltd.
Consultants
Consultants
M/s. Rahul Deshpande & Associates
3

Landscaping work.

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2004
Stipulated Date of Completion /
Likely Date of Completion
May 25 2004
Status
100%
Completed
Cost (₹)
Awarded for ₹ 97,000.00
 
Contractors
Contractors
M/s. Hariyalee Nursery
Consultants
Consultants
M/s. Rahul Deshpande & Associates
4

Signages.

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2004
Stipulated Date of Completion /
Likely Date of Completion
May 25 2004
Status
100%
Completed
Cost (₹)
Awarded for ₹ 133,883.00
 
Contractors
Contractors
M/s. Home Deco
Consultants
Consultants
M/s. Rahul Deshpande & Associates
Similar Projects

See Similar Projects

Similar Project

Design and Construction of Nuem – Cola Bridge including approach road in Canacona Taluka.

View Project
Similar Project

Improvement and Upgradation of the existing MDR from Dandevaddo to Chandor via Sarzora and Guddi in Cuncolim Constituency.

View Project
Similar Project

Improvement / Widening of road in Saligao – Calangute Constituency.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.