Project Duration
Stipulated Date of Commencement March 27 2007
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at ₹ 203,081,980.00
Awarded for ₹ 228,194,428.97
Final Cost of Project ₹ 472,055,944.00
 
Contractors
M/s. D. S. Contractors Pvt. Ltd., M/s. D. S. Contractors Pvt. Ltd., M/s. D. S. Contractors Pvt. Ltd.
Consultants
M/s. Effective Architectural Services, M/s. Effective Architectural Services, M/s. Effective Architectural Services
 