Project Duration
Stipulated Date of Commencement
January 23 2019
Actual Date of Completion
March 10 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,68,85,072.00.
Awarded for
₹ 19,212,281.50
Final Cost of Project
₹ 17885831
Contractors
M/s. T. S. Mistry
Consultants
M/s. UCJ Architecture & Environment
See Similar Projects
CCTV Works
View ProjectMinor Maintenance/ Renovation works at Goa Medical College and Hospital, including Hospitals and Health Centre’s under the jurisdiction of Goa Medical College (2018-2019)
View ProjectDevelopment Plan of the site of Shree Mahalasa Devi Temple at Verna-Phase I
View Project