Project Duration
Stipulated Date of Commencement
October 09 2012
Stipulated Date of Completion /
Likely Date of Completion June 10 2012
Likely Date of Completion June 10 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,016,258.00
Awarded for
₹ 13,083,870.45
Project highlights
Foreclosed.
GSIDC in its 124th Board Meeting held on 28th November 2013, vide Resolution No.3367, resolved to foreclose the Contract of M/s. Indiana Build Infrastructure Pvt. Ltd.
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Consultants
M/s. Effective Architectural Services