Project Duration
Stipulated Date of Commencement October 07 2016
Actual Date of Completion February 29 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 19,496,816.00
Awarded for ₹ Rs.2,38,08,805.00

Project highlights

Connection of houses to main sewer lines

 
Contractors
M/s. Jagadish V. Pai
Consultants
M/s. En-vision Enviro Technologies Pvt. Ltd.
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Construction Of Sewage Treatment Plant At Sanquelim, Goa-Transformer And Dg Works

100% completed
 
Project Duration
Stipulated Date of Commencement February 28 2014
Stipulated Date of Completion /
Likely Date of Completion
July 11 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,216,737.00
Awarded for ₹ 3,626,240.00
Final Cost of Project ₹ 4,137,986.00

Project highlights

The scope of work involves supply and installation of Tranformer and DG Set.

 
Contractors
M/S Arken Solutions Pvt. Ltd.
Consultants
Inhouse (GSIDC)
2

Construction STP Sanquelim – Compound Wall & Allied work.

100% completed
 
Project Duration
Stipulated Date of Commencement September 18 2015
Stipulated Date of Completion /
Likely Date of Completion
February 26 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,534,100.49
Awarded for ₹ 1,929,173.76
Final Cost of Project ₹ 1,842,303.00

Project highlights

Compound wall was constructed around the STP at Sanquelim

 
Contractors
M/s. Deepak Marathe
Consultants
In House

See Similar Projects

The Building for KTC Bus Stand Pedne

View Project

Construction of Forest Headquarters Building at Altinho Old IPHB Complex

View Project

Upgradation of Pay Ward at Goa Medical College, Bambolim, Goa – Additional furniture works

View Project
x