Project Duration
Stipulated Date of Commencement
October 29 2007
Stipulated Date of Completion /
Likely Date of Completion November 12 2007
Likely Date of Completion November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,517,253.00
Awarded for
₹ 3,910,525.00

Contractors
M/s. Max Alert Systems Pvt. Ltd

Consultants
M/s. Effective Architectural Services