Status
100%
Completed
Contractors
Consultants
Sub Works
This project involved 6 sub works. The details of the same available below
1
Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).
100% completed
Project Duration
Stipulated Date of Commencement
May 25 2011
Stipulated Date of Completion /
Likely Date of Completion September 25 2011
Likely Date of Completion September 25 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,882,049.00
Awarded for
₹ 4157111.35
Contractors
M/s. Rakesh Bandekar,
Consultants
M/s. Datta Kare Associates
2
Construction of Anganwadi Centres from NABARD Assistance – Package III (GPS Pernem, GPS Mandrem, GPS Korgao).
100% completed
Project Duration
Stipulated Date of Commencement
December 29 2011
Stipulated Date of Completion /
Likely Date of Completion July 28 2012
Likely Date of Completion July 28 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,526,892.00
Awarded for
₹ 7179487.8
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
3
Construction of Anganwadi Centres from NABARD Assistance – Package IV (GPS Chandel, GPS Ibrampur, GPS Hansapur).
100% completed
Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion October 05 2011
Likely Date of Completion October 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,683,732.52
Awarded for
₹ 6086790.88
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates
4
Construction of Anganwadi Centres from NABARD Assistance – Package V (GPS Kajrechi Vhali, GPS Dhangarwada Bhuipal, GPS Ghoteli No.1)
100% completed
Project Duration
Stipulated Date of Commencement
December 28 2010
Stipulated Date of Completion /
Likely Date of Completion March 28 2011
Likely Date of Completion March 28 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,166,556.00
Awarded for
₹ 6632510.73
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Datta Kare Associates
5
Construction of Anganwadi Centres from NABARD Assistance – Package VI (GPS Betmoddi Kakoda, GPS Bendurdem, GPS Cumbeabhat Velim).
100% completed
Project Duration
Stipulated Date of Commencement
September 22 2011
Stipulated Date of Completion /
Likely Date of Completion June 21 2012
Likely Date of Completion June 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,062,925.00
Awarded for
₹ 6669089.99
Project highlights
Construction of Anganwadi Centres
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
6
Construction of Anganwadi Centres from NABARD Assistance – Package VII (GPS Bethoda).
100% completed
Project Duration
Stipulated Date of Commencement
October 17 2011
Stipulated Date of Completion /
Likely Date of Completion February 16 2012
Likely Date of Completion February 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,834,743.14
Awarded for
₹ 2006449.53
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
See Similar Projects
Road and external storm water drainage works.
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package L (Sattari Taluka) – (GPS Barazan, GPS Khadki, GPS Velge, GPS Khotode)
View Project
Readymade Furniture work
View Project





