Project Duration
Stipulated Date of Commencement
December 30 2016
Stipulated Date of Completion /
Likely Date of Completion April 15 2021
Likely Date of Completion April 15 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 69,812,937.00
Awarded for
₹ 60,183,352.75
Project highlights
Metal False Ceiling, Calcium silicate false ceiling work
Contractors
M/s. Deshpande Constructions
Consultants
M/s. KICONS Limited