Project Duration
Stipulated Date of Commencement December 30 2016
Stipulated Date of Completion /
Likely Date of Completion
April 15 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 69,812,937.00
Awarded for ₹ 60,183,352.75

Project highlights

Metal False Ceiling, Calcium silicate false ceiling work

 
Gallery Image
Contractors
M/s. Deshpande Constructions
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

S.H. Carriage of Water for 3 years

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Medical Gas Pipelines.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – S.H- Maintenance /Renovation work of Community Health Center at Canacona – Maintenance Contract for Schindler Elevator installed at Canacona CHC

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.