Project Duration
Stipulated Date of Commencement February 28 2014
Actual Date of Completion August 31 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 92,020,305.00
Awarded for ₹ 110,973,898.96
Final Cost of Project ₹ 128,563,400.00

Project highlights

This is an examination hall with auditorium of capacity of 250 students

 
Contractors
M/s. Indage Development Construction Pvt. Ltd
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 