Project Duration
Stipulated Date of Commencement
February 17 2011
Stipulated Date of Completion /
Likely Date of Completion July 16 2011
Likely Date of Completion July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,087,400.00
Awarded for
₹ 2,220,000.00
Contractors
M/s. Eagle Construction Co.
Consultants
Datta Kare Associates