Project Duration
Stipulated Date of Commencement February 17 2011
Stipulated Date of Completion /
Likely Date of Completion
July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,087,400.00
Awarded for ₹ 2,220,000.00
 
Gallery Image
Contractors
M/s. Eagle Construction Co.
Gallery Image
Consultants
Datta Kare Associates
 