Project Duration
Stipulated Date of Commencement
July 15 2004
Actual Date of Completion
April 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 140,325,985.00
Awarded for
₹ 147,280,036.00
Final Cost of Project
₹ 210,585,735.00
Contractors
M/s. Nagarjuna Construction Company Ltd., M/s. Nagarjuna Construction Company Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd