Project Duration
Stipulated Date of Commencement
March 18 2019
Stipulated Date of Completion /
Likely Date of Completion May 17 2019
Likely Date of Completion May 17 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 468,019.00
Awarded for
₹ 464,915.00
Project highlights
Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.
View Project
Construction of subway at Bambolim – Civil works
View Project
Rear Side parking and Biomedical Waste Building
View Project