Project Duration
Stipulated Date of Commencement
February 10 2014
Stipulated Date of Completion /
Likely Date of Completion March 09 2014
Likely Date of Completion March 09 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 413,733.00
Awarded for
₹ 398,600.00
Contractors
M/s. Reconnoitre Systems.,
Consultants
In-house (GSIDC)