Project Duration
Stipulated Date of Commencement
February 23 2013
Stipulated Date of Completion /
Likely Date of Completion August 22 2013
Likely Date of Completion August 22 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,832,122.81
Awarded for
₹ 6,839,446.96
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.