Project Duration
Stipulated Date of Commencement
December 17 2018
Actual Date of Completion
August 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,003,936.00
Awarded for
₹ 8,936,969.00
Final Cost of Project
₹ 8,743,744.12
Project highlights
Interior work
Contractors
M/s. Creation Interiors
Consultants
M/s. FP Project Management