Project Duration
Stipulated Date of Commencement
August 20 2010
Stipulated Date of Completion /
Likely Date of Completion May 19 2011
Likely Date of Completion May 19 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 30,789,278.00
Awarded for
₹ 32,313,347.00
Project highlights
Beautification work by providing pavers for footpaths and hotmixing of certain internal roads in Sanguem town
Contractors
M/s.Shilpi Constructions
Consultants
In-house (GSIDC)