Project Duration
Stipulated Date of Commencement June 19 2023
Stipulated Date of Completion /
Likely Date of Completion
August 02 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,405,012.00
Awarded for ₹ 1,303,226.76

Project highlights

Infrastructure for setting up of 6 Bedded Dialysis Unit

 
Gallery Image
Contractors
M/s. Concept Creators
Gallery Image
Consultants
M/s. Saolapurkar and Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Medical Gas Pipelines.

View Project
Similar Project

Supply, Testing and Commissioning of Battery Operated Sternal Saw and Electrically operated Sternal Saw

View Project
Similar Project

Supply, Installation and Testing and Commissioning of Blood warmer

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.