Project Duration
Stipulated Date of Commencement
September 26 2013
Stipulated Date of Completion /
Likely Date of Completion January 25 2014
Likely Date of Completion January 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,324,109.94
Awarded for
₹ 5,899,999.00
