Project Duration
Stipulated Date of Commencement
March 23 2021
Stipulated Date of Completion /
Likely Date of Completion March 30 2021
Likely Date of Completion March 30 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,080.00
Awarded for
₹ 42,080.00
Project highlights
Supply of 20ft X 30 ft Indian National Flag
Contractors
M/s. Advertising Flag
Consultants
In-house (GSIDC)