Project Duration
Stipulated Date of Commencement
May 26 2006
Stipulated Date of Completion /
Likely Date of Completion August 25 2006
Likely Date of Completion August 25 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 32,030,672.33
Awarded for
₹ 39,367,547.00
Project highlights
Road widening & improvement of existing road network from Borim bridge junction to Kamaxi temple and Shivnath temple in Shiroda
Contractors
M/s. Ritesh Developers Pvt. Ltd
Consultants
M/s. Keni & D’Souza
See Similar Projects
Demolition of old Existing jetty and Reconstruction of New Fisheries Jetty at Panaji, Goa
View Project
Construction of Bus Stand & Mini Depot at Sankhali, Goa – Erection of 11KV line from Electricity Department feeder to bus stand substation.
View Project
Conversion of Overhead Lines to underground system and installation of 11KV & LT equipment’s along the road from NIO circle to Dona Paula Jetty and NIO circle to Rajbhavan road
View Project





