Project Duration
Stipulated Date of Commencement April 05 2016
Stipulated Date of Completion /
Likely Date of Completion
August 04 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 30,493,196.00
Awarded for ₹ 29,129,514.00

Project highlights

Conversion of overhead lines to underground system and installation of 11KV & LT equipment’s

 
Gallery Image
Contractors
M/s. Sudha Electric Co.
Gallery Image
Consultants
M/s LKS India Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Hotmixing of Road from Sai Service Junction to Training College Junction at Porvorim, Goa

View Project
Similar Project

Phase II : Civil & Electrical works

View Project
Similar Project

Demolition of Old existing jetty and Reconstruction of New Captain of Ports jetty at Old Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.