Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion May 26 2015
Likely Date of Completion May 26 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,67,33,007.00
Awarded for
₹ 17,84,08,183.39
Project highlights
The jetty is a T-shaped fixed piled concrete jetty, with two concrete floating pontoons and permanent piled concrete berthing dolphins. The T-shaped fixed piled concrete jetty provides access to the two concrete floating pontoons which weighs 180 tons each and which are in turn berthing dolphins that ensure the concrete floating pontoon move only along the Z-axis by means of system of stainless steel yokes.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Kashec Engineers Pvt. Ltd.
See Similar Projects
Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14
View Project
Design and Construction of bridge at Patto in Panaji including approach roads
View Project
Widening of road in Calangute – Baga – Electrical works..
View Project