Project Duration
Stipulated Date of Commencement June 30 2007
Stipulated Date of Completion /
Likely Date of Completion
September 30 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 54,521,530.00
Awarded for ₹ 70,197,527.00

Project highlights

Restoration works

 
Gallery Image
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Gallery Image
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Maintenance of Buildings under Directorate of Food & Drugs Administrative, Bambolim-Goa. S.H.- Maintenance Contract for the 180 KVA Diesel Generator set installed at Directorate of Food and Drugs Administration, Bambolim for Three years.

View Project
Similar Project

Resurfacing of main road from Miramar Circle to NIO Circle for IFFI 2012.

View Project
Similar Project

Minor Maintenance / Renovation works at Hospitals, Health Centres and Institutions under Directorate of Health Services, in the State of Goa – Roofing works (Balance Works)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.